Open earthworks, access tracks and equipment along the SuedLink cable corridor near Hüngheim.
← Back to projects

Infrastructure / Energy

SuedLink

Cost forecasting and performance reporting for SuedLink project controls.

Germany · Süd 01 / C2
SuedLink construction near Hüngheim, 16 June 2025. This view illustrates the wider programme, outside my Süd 01 / C2 work package.Granpar · CC BY-SA 3.0 · Source
My roleSenior Associate · Project Controls & PMO
OrganisationPwC Germany · Capital Projects & Infrastructure
My involvementMarch 2024 – October 2025
Scope of workSüd 01 · Section C2

01Project context

An energy corridor across Germany.

My assignment at PwC covered cost and performance monitoring for SuedLink Süd 01, section C2, lot 4. The work connected technical and commercial reporting within the project management office (PMO).

The task

As design, approvals, procurement and construction preparation progressed, reports needed to reflect changing conditions. A consistent baseline made cost movements and progress easier to assess across the technical and commercial teams.

02My responsibilities

The responsibilities described here were carried out within the named organisation and project team.

  1. 01

    Maintained cost calculations and developed and updated baselines for cost and performance analysis.

  2. 02

    Contributed forecasts and reports using RIB iTWO data, Power BI and Earned Value Management.

  3. 03

    Aligned reporting inputs across technical, commercial and PMO teams, organised workshops and supported coordination with construction partners.

Methods & tools

RIB iTWOBaseline trackingEVMPower BIP6 · Tilos · JIRA · tpCDE

Deliverables

  • Updated cost calculations, reporting baselines, forecasts and performance analyses.
  • Coordinated reporting inputs and workshop material for technical and commercial teams.

Project location

Two connections. One programme.

The schematic shows the connection points and section C2 in context. My work concerned the Süd 01 / C2 package described above, rather than the entire corridor.

Original schematic · not to scale · not an approved route alignment. C2 source: May 2023.

Official plans & sources

Current official project overviewOverall route · official PDF, map dated 09/2022C2 location plan · official PDF, 05/2023
Read a text description

Brunsbüttel to Großgartach/Leingarten; Wilster to Bergrheinfeld/West. Separate C2 context: Neu-Eichenberg to Herleshausen.

The links lead to original plans on the official project websites. This overview provides context and does not replace a technical location plan.